_aBuilding _v264(8117) 17 December 1999, 46(1) |
||
| 520 | _aArgues for and against trying to enforce a contract clause that requires a bond and guarantee from a supplier, as illustrated by "Chiemgauer Membran und Zeltbau GmbH (Koch) v New Millennium Experience Company Ltd". | ||
| 590 | _aABS | ||
| 650 | _aPROCEDURAL OBLIGATIONS | ||
| 650 | _aCONTRACT CLAUSES | ||
| 650 | _aCHIEMGAUER MEMBRAN UND ZELTBAU GMBH (KOCH) V NEW MILLENNIUM EXPERIENCE COMPANY LTD | ||
| 650 | _aPERFORMANCE BONDS | ||
| 690 | _aBUILT ENVIRONMENT-BUILDING CONTRACT FORMS | ||