| 000 | 01012cam a2200217 4500 | ||
|---|---|---|---|
| 001 | ABS62314 | ||
| 008 | 000000n2000 000 0 eng u | ||
| 035 | _a(Sirsi) u106185 | ||
| 100 | _aBrewer, G. | ||
| 245 | _aDouble indemnity | ||
| 260 | _c2000 | ||
| 490 |
_aContract Journal _v403(6275) 4 May 2000, 30(1) |
||
| 520 | _aDiscusses the case "Herschel Engineering Ltd v Breen Property Ltd" which held that there was nothing within the statutory provisions to prevent an adjudication from proceeding concurrently with any court proceedings in respect of the same disputed matter. | ||
| 590 | _aABS | ||
| 650 | _aHERSCHEL ENGINNERING LTD V BREEN PROPERTY LTD | ||
| 650 | _aMANAGEMENT-DISPUTE AVOIDANCE, MANAGEMENT AND RESOLUTION-DISPUTE MANAGEMENT AND RESOLUTION-ALTERNATIVE DISPUTE RESOLUTION-ADJUDICATION | ||
| 650 | _aLITIGATION | ||
| 650 | _aMANAGEMENT-DISPUTE AVOIDANCE, MANAGEMENT AND RESOLUTION-DISPUTE MANAGEMENT AND RESOLUTION-ARBITRATION | ||
| 690 |
_aDispute resolution _96236 |
||
| 942 | _n0 | ||
| 999 |
_c63613 _d63613 |
||