245 _aDouble indemnity
260 _c2000
490 _aContract Journal
_v403(6275) 4 May 2000, 30(1)
520 _aDiscusses the case "Herschel Engineering Ltd v Breen Property Ltd" which held that there was nothing within the statutory provisions to prevent an adjudication from proceeding concurrently with any court proceedings in respect of the same disputed matter.
590 _aABS
650 _aHERSCHEL ENGINNERING LTD V BREEN PROPERTY LTD
650 _aMANAGEMENT-DISPUTE AVOIDANCE, MANAGEMENT AND RESOLUTION-DISPUTE MANAGEMENT AND RESOLUTION-ALTERNATIVE DISPUTE RESOLUTION-ADJUDICATION
650 _aLITIGATION
650 _aMANAGEMENT-DISPUTE AVOIDANCE, MANAGEMENT AND RESOLUTION-DISPUTE MANAGEMENT AND RESOLUTION-ARBITRATION
690 _aDispute resolution