| 520 | _aDiscusses an adjudicator's decision in "Bloor Constuction (UK) Ltd v Bowmer and Kirkland (London) Ltd". The adjudicator made a clerical error concerning the amount of money to be paid. He acknowledged the error and corrected the figures by the end of the day but Bloor claimed the correction was too late and went to the High Court to enforce. The judge decided that provided the parties do not expressly ban a slip rule in the contract, an adjudicator can correct an admitted accidental slip or omission. | ||
| 590 | _aABS | ||
| 650 | _aARBITRATORS | ||
| 650 | _aARBITRATION ACT 1996 | ||
| 650 | _aSLIP RULE | ||
| 650 | _aSCHEME FOR CONSTRUCTION CONTRACTS | ||
| 650 | _aIMPLIED TERMS | ||
| 690 |
_aDispute resolution _96236 |
||
| 942 | _n0 | ||
| 999 |
_c63740 _d63740 |
||