520 _aExamines "Bridgeway Construction Ltd v Tolent Construction Ltd" in which Tolent placed a groundwork subcontract with Bridgeway that was on Tolent's home-made terms. The subcontract agreement stated that if a subcontractor calls for a referee, regardless of who wins, the subcontractor has to pay Tolent's adjudication costs. Tolent contends this clause is to deter 'spurious claims'. The article questions the worth of the clause.
590 _aABS
650 _aBRIDGEWAY CONSTRUCTION LTD V TOLENT CONSTRUCTION LTD
650 _aBEST VALUE
650 _aMANAGEMENT-DISPUTE AVOIDANCE, MANAGEMENT AND RESOLUTION-DISPUTE MANAGEMENT AND RESOLUTION-ALTERNATIVE DISPUTE RESOLUTION-ADJUDICATION
650 _aCOSTS
650 _aSUBCONTRACTORS
650 _aREFEREES
650 _aSUBCONTRACT AGREEMENTS