| 245 | _aWhen payment is held back with impunity | ||
| 260 | _c2000 | ||
| 490 |
_aConstruction News _v(6684) 21 September 2000, 44(1) |
||
| 520 | _aDiscusses the decision in "Whiteways Contractors v Impresa Castelli Construction" which established that notice under the Housing Grants, Construction and Regenration Act s110(2) or s111 is required to withold payment, whether by means of set-off or abatement. | ||
| 590 | _aABS | ||
| 650 | _aWHITEWAYS CONTRACTORS (SUSSEX) LTD V IMPRESA CASTELLI CONSTRUCTION UK LTD | ||
| 650 | _aINTERIM VALUATIONS | ||
| 650 | _aMANAGEMENT-DISPUTE AVOIDANCE, MANAGEMENT AND RESOLUTION-DISPUTE MANAGEMENT AND RESOLUTION-ALTERNATIVE DISPUTE RESOLUTION-ADJUDICATION | ||
| 650 | _aNON-PAYMENT | ||
| 650 | _aS111 NOTICES | ||