| 245 | 4 | _aThe final straw | |
| 260 | _c2000 | ||
| 490 |
_aBuilding _v265(8153) 15 September 2000, 83(1) |
||
| 520 | _aDiscusses "Shepherd Construction v Mecright Ltd", which highlights some important points for those considering seeking adjudication. Firstly, that it is wrong to begin an adjudication in the face of an existing settlement agreement on the final account. Secondly, when referring to adjudication it is imperative that a dispute is presented in full, including both sides' views. | ||
| 590 | _aABS | ||
| 650 | _aMANAGEMENT-DISPUTE AVOIDANCE, MANAGEMENT AND RESOLUTION-DISPUTE MANAGEMENT AND RESOLUTION-ALTERNATIVE DISPUTE RESOLUTION-ADJUDICATION | ||
| 650 | _aCONSTRUCTION DISPUTES | ||
| 650 | _aCONTRACT CLAIMS | ||
| 650 | _aSHEPHERD CONSTRUCTION V MECRIGHT | ||
| 690 |
_aDispute resolution _96236 |
||