000 01696cam a2200253 4500
001 ABS63522
008 000000n2000 000 0 eng u
035 _a(Sirsi) u110871
245 _aHenry Boot Construction Ltd v Alstom Combined Cycles Ltd
260 _c2000
490 _aConstruction Law Journal
_v[2000] 16 Const.L.J. 6, 400-413(14)
520 _aCA 4 April 2000. Boot was the civil engineering contractor for a combined cycle gas turbine power station being built by Alstom. The contract used was the ICE 6th Edition with modifications. The contract price was £250,880 for certain temporary works. It became necessary to value increases under clause 52(1)(b) of the contract. The valuation was carried out with reference to the original valuation of the temporary works. However, the price was based on a mistake in favour of Boot. The arbitrator concluded it was not reasonable to use a price where the price reached was calculated in error, and decided that clause 52(2) should be applied in order to produce a fair valuation. It was concluded that the arbitrator should have based the valuation of the increased values on the price of £250,880, and it was not within the remit of the arbitrator to correct the mistake. Alstom appealed. "Held" appeal by Alstom dismissed.
590 _aABS
650 _aVARIATIONS
650 _aCONTRACT CLAIMS
650 _aENGINEERING CONTRACTS
650 _aICE CONDITIONS OF CONTRACT (SIXTH EDITION)
650 _aVALUATION OF VARIATIONS
650 _aBILLS OF QUANTITIES
650 _aREASONABLENESS
650 _aHENRY BOOT CONSTRUCTION V ALSTOM COMBINED CYCLES
690 _aBUILDING AND CONSTRUCTION-CASE LAW
942 _n0
999 _c66092
_d66092