000 01491cam a2200241 4500
001 ABS63523
008 000000n2000 000 0 eng u
035 _a(Sirsi) u110901
245 _aHescorp Italia spa v Morrison Construction Ltd and Impregilo UK Ltd
260 _c2000
490 _aConstruction Law Journal
_v[2000] 16 Const.L.J. 6, 413-424(11)
520 _aTCC 17 March 2000. Claimant applied for a summary judgement under CPR Part 24 together with an interim payment under CPR Part 25.7. The claimant and defendant were negotiating the conditions and obligations of the proposed steelwork sub-contract. During this period, the claimant started work and reached completion of the work, although there was still no signed contract. Claimant maintained they were entitled to be paid on a "quantum meruit" as there was still no formal contract. Defendant alleged that a contract was entered into, in an informal manner during correspondence, and that it was entitled to set off a counterclaim for breaches of contract, including liquidated damages for delay. "Held" applications adjourned. See ABS62131
590 _aABS
650 _aBUILT ENVIRONMENT-BUILDING CONTRACT FORMS
650 _aCOMPLETION DATES
650 _aDAMAGES
650 _aQUANTUM MERUIT
650 _aINTERIM PAYMENTS
650 _aSUMMARY JUDGMENTS
650 _aHESCORP ITALIA SPA V MORRISON CONSTRUCTION LTD AND IMPREGILO UK LTD
690 _aBUILDING AND CONSTRUCTION-CASE LAW
942 _n0
999 _c66102
_d66102