245 _aPrinciple of adjudication must remain
260 _c2001
490 _aConstruction News
_v(6720) 14 June 2001, 12(2)
520 _aStudies the Scheme for Construction Contracts para 20(a) which has encouraged many main contractors to declare that virtually everything in their subcontracts is 'final and conclusive', in a bid to sidestep adjudication. This runs counter to the spirit and letter of the Construction Act, which confers on a party the right to refer any dispute under the contract to adjudication. The DETR should amend para 20(a) to prevent this conflict between secondary and primary legislation.
590 _aWB
650 _aMANAGEMENT-DISPUTE AVOIDANCE, MANAGEMENT AND RESOLUTION-DISPUTE MANAGEMENT AND RESOLUTION-ALTERNATIVE DISPUTE RESOLUTION-ADJUDICATION
650 _aHOUSING GRANTS, CONSTRUCTION AND REGENERATION ACT 1996
650 _aSCHEME FOR CONSTRUCTION CONTRACTS PARA 20(A)
690 _aDispute resolution