| 245 | _aPrinciple of adjudication must remain | ||
| 260 | _c2001 | ||
| 490 |
_aConstruction News _v(6720) 14 June 2001, 12(2) |
||
| 520 | _aStudies the Scheme for Construction Contracts para 20(a) which has encouraged many main contractors to declare that virtually everything in their subcontracts is 'final and conclusive', in a bid to sidestep adjudication. This runs counter to the spirit and letter of the Construction Act, which confers on a party the right to refer any dispute under the contract to adjudication. The DETR should amend para 20(a) to prevent this conflict between secondary and primary legislation. | ||
| 590 | _aWB | ||
| 650 | _aMANAGEMENT-DISPUTE AVOIDANCE, MANAGEMENT AND RESOLUTION-DISPUTE MANAGEMENT AND RESOLUTION-ALTERNATIVE DISPUTE RESOLUTION-ADJUDICATION | ||
| 650 | _aHOUSING GRANTS, CONSTRUCTION AND REGENERATION ACT 1996 | ||
| 650 | _aSCHEME FOR CONSTRUCTION CONTRACTS PARA 20(A) | ||