| 245 | _aCough-up medicine | ||
| 260 | _c2001 | ||
| 490 |
_aBuilding _v266(8198) 17 August 2001, 39(1) |
||
| 520 | _aExamines one of the main aims of the Construction Act; ensuring payment. Uses two cases, "Re a company" (no 1299 of 2001) and "Millers Specialist Joinery Co Ltd v Nobles Construction Ltd", to illustrate that where money is owed and no withholding notices issued, the payment should be made as the payee, after the final date, can claim the amount as a clean debt. | ||
| 590 | _aABS | ||
| 650 | _aHOUSING GRANTS, CONSTRUCTION AND REGENERATION ACT 1996 | ||
| 650 | _aWITHHOLDING NOTICES | ||
| 650 | _aRE A COMPANY (NO 1299 OF 2001) | ||
| 650 | _aMILLERS SPECIALIST JOINERY LTD V NOBLES CONSTRUCTION LTD | ||
| 650 | _aMANAGEMENT-DISPUTE AVOIDANCE, MANAGEMENT AND RESOLUTION-DISPUTE MANAGEMENT AND RESOLUTION-ALTERNATIVE DISPUTE RESOLUTION-ADJUDICATION | ||