100 _aBingham, T
245 _aSynchronise watches
260 _c2001
490 _aBuilding
_v266(8207) 23 November 2001, 50-51(2)
520 _aDiscusses the case "Sindall Ltd v Solland" which deals with two key issues. Sindall failed to give contract administrator Michael Edwards & Associates (MEA) enough time to respond to its complaint before starting adjudication which meant the first adjudicator had no right to adjudicate; MEA accused Sindall of not proceeding reasonably and diligently yet failed to give Sindall the correct extension of time which meant MEA had no grounds for giving notice.
590 _aABS
650 _aMANAGEMENT-DISPUTE AVOIDANCE, MANAGEMENT AND RESOLUTION-DISPUTE MANAGEMENT AND RESOLUTION-ALTERNATIVE DISPUTE RESOLUTION-ADJUDICATION
650 _aSINDALL LTD V SOLLAND
650 _aDISPUTE RESOLUTION
_96236
650 _aCONSTRUCTION DISPUTES
650 _aEXTENSION OF TIME