100 _aBingham, T
245 _aIndecent proposals
260 _c2002
490 _aBuilding
_v267(8229) 12 April 2002, 48-49(2)
520 _aLooks at claims by unsuccessful parties to an adjudication to set-off the amount to be paid under the decision by sums owed to it by the successful party. Reviews "Robert McAlpine v Pring St Hill" (2001) where the contractor brought enforcement proceedings and in which the defendant subcontractor made a set-off claim. Highlights the subcontractor's argument on the requirements of the Housing Grants, Construction and Regeneration Act 1996.
590 _aABS
650 _aROBERT MCALPLINE V PRING ST HILL
650 _aHOUSING GRANTS CONSTRUCTION AND REGENERATION ACT 1996
650 _aSET-OFF CLAIMS
650 _aSUBCONTRACTORS
650 _aMANAGEMENT-DISPUTE AVOIDANCE, MANAGEMENT AND RESOLUTION-DISPUTE MANAGEMENT AND RESOLUTION-ALTERNATIVE DISPUTE RESOLUTION-ADJUDICATION