| 245 | _aAtlas Ceiling and Partition Company Limited v Crowngate Estates (Cheltenham) Limited | ||
| 260 | _c2002 | ||
| 490 |
_aConstruction Law Journal _v[2002] Const L J 49-55(7) |
||
| 520 | _aQBD 18 February 2000 Defendant (C) was main contractor on project with claimant (A). Work began January 1998 pursuent to letter of intent dated 18 December 1997. 3 April 1998 DOM/1 signed by each party. C contended contract entered into that day. A contended contract undated, and contract not entered into until after 1 May 1998. C referrred claim to adjudication under HGCRA. Decision dated 14 January 2000 found for C against A. A sought enforcement. C contended contract entered into 3 April 1998, and challenged adjudicators jurisdiction. "Held" that contract between parties took effect from 12 April 1999 and was not a variation of the earlier letter of intent. | ||
| 590 | _aABS | ||
| 650 | _aATLAS CEILING AND PARTITION COMPANY LIMITED V CROWNGATE ESTATES (CHELTENHAM) LIMITED | ||
| 650 | _aMANAGEMENT-DISPUTE AVOIDANCE, MANAGEMENT AND RESOLUTION-DISPUTE MANAGEMENT AND RESOLUTION-ALTERNATIVE DISPUTE RESOLUTION-ADJUDICATION | ||
| 650 | _aDOM/1 | ||
| 690 | _aMANGEMENT-DISPUTE AVOIDANCE, MANAGEMENT AND RESOLUTION-DISPUTE MANAGEMENT AND RESOLUTION | ||