520 _aTCC 21 March 2002. C refused to comply with an adjudicator's decision in favour of N in proceedings for an extension of time and loss and expense on the grounds that there were significant differences from the original claim in the factual justification for and quantification of loss and expense in the expert's report accompanying the referral notice and that this was effectively a different claim. The judge ruled in favour of C stating that a party must submit to adjudication the facts and arguments previously rehearsed between the party.
590 _aABS
650 _aEDMUND NUTTALL LTD V R G CARTER LTD
650 _aEXTENSIONS OF TIME
650 _aMANAGEMENT-DISPUTE AVOIDANCE, MANAGEMENT AND RESOLUTION-DISPUTE MANAGEMENT AND RESOLUTION-ALTERNATIVE DISPUTE RESOLUTION-ADJUDICATION
690 _aMANGEMENT-DISPUTE AVOIDANCE, MANAGEMENT AND RESOLUTION-DISPUTE MANAGEMENT AND RESOLUTION
942 _n0
999 _c70425
_d70425