520 _aBuilding Cost Information Service's (BCIS) latest "Contract percentages study" shows that tender preliminaries reached their highest level for nearly 25 years in the second quarter of 2002, averaging 14.7% as a percentage of total contract sums (excluding contingencies. The BCIS study charts preliminaries and profit and overhead percentages on prime cost sums and dayworks from recent contract. It is published in the BCIS "Surveys of tender prices" and is available from BCIS either as part of their bulletin subscription service or individual copies at £90.00 t+44 (0)20 7695 1500 BCIS website http://www.bcis.co.uk/