245 _aHeed the words of warning
260 _c2003
490 _aConstruction News
_v(6811) 10 April 2003, 47(1)
520 _aIn "Sahib Foods Ltd and another v Paskin Kyriakides Sands" ([2003] EWHC 142 (TCC), X121974) claimant (S) had employed the defendant (P) to design the refurbishment of its food processing factory in 1995. When it was mostly destroyed by fire in 1998, S sued P for its losses. P had not followed advice to install non-combustible wall panels in a vulnerable room and S's staff had been negligent in allowing a fire to start. Judge found P liable for the damages caused by the fire once it damaged the rest of the factory, having not been contained in the original room. Advises that once a danger has been highlighted it should be acted on or the decision may cause future problems. View judgment at www.courtservice.gov.uk
590 _aABS
650 _aSAHIB FOODS LTD AND ANOTHER V PASKIN KYRIAKIDES SANDS
650 _aWALL CLADDING
650 _aFACTORY BUILDINGS
650 _aFIRE CONTROL
650 _aNEGLIGENCE
690 _aMANGEMENT-DISPUTE AVOIDANCE, MANAGEMENT AND RESOLUTION-DISPUTE MANAGEMENT AND RESOLUTION
856 _uhttps://www.bailii.org/cgi-bin/markup.cgi?doc=/ew/cases/EWHC/TCC/2003/142.html&query=sahib+and+foods&method=boolean
_zView the judgment free of charge at www.bailii.org