| 245 | _aLate adjudication decisions | ||
| 260 | _c2003 | ||
| 490 |
_aContract Journal _v418(6425) 8 May 2003, 14 |
||
| 490 |
_aConstruction News _v(6818) 29 May 2003, 12(2) |
||
| 520 | _aA recent case "St Andrews Bay Development Ltd v H B G Management Ltd" (CSOH 20 March 2003, [2003] CILL 2016 dealt with whether an adjudicator can delay the delivery of the decision pending payment of their fees. St Andrews (A) had employed H B G (H) to build a leisure complex. The arising disputes were referred to an adjudicator. After reaching a decision the adjudicator decided to withhold their decision until their fees were paid. A contested the decision as they believed it had been issued after the date it was due and argued that a decision reached but not communicated is no decision at all. A applied to have the decision set aside, but this was refused by the appeal court on the grounds that this fundamental error should not nullify the entire decision. View judgment at www.scotcourts.gov.uk. | ||
| 590 | _aABS | ||
| 650 | _aMANAGEMENT-DISPUTE AVOIDANCE, MANAGEMENT AND RESOLUTION-DISPUTE MANAGEMENT AND RESOLUTION-ALTERNATIVE DISPUTE RESOLUTION-ADJUDICATION | ||
| 650 | _aPAYMENTS | ||
| 650 | _aHOUSING GRANTS, CONSTRUCTION AND REGENERATION ACT 1996 | ||
| 650 | _aST ANDREWS BAY DEVELOPMENT LTD V H B G MANAGEMENT LTD | ||
| 690 | _aMANGEMENT-DISPUTE AVOIDANCE, MANAGEMENT AND RESOLUTION-DISPUTE MANAGEMENT AND RESOLUTION | ||
| 856 |
_uhttps://www.scotcourts.gov.uk/opinions/p370_03.html _zView the judgment free of charge at www.scotscourts.gov.uk |
||