100 _aElliott, T.
245 _aConstruction of contracts
260 _c1996
350 _a0
490 _aBuilding
_v261(7934) 29 March 1996, 35(1)
520 _aDiscusses "North West Thames Health Authority v Sheppard Robson and others" 1996 concerning the construction of subcontracts between the management contractor and its subcontractors. The main contract and the subcontracts were closely interwoven. The obligation of the authority to pay the contractor extra when the project overran was dependent on the construction of the subcontracts.
650 _aBUILT ENVIRONMENT-BUILDING CONTRACT FORMS
650 _aCLAIMS
650 _aMANAGEMENT CONTRACT
650 _aNORTH WEST THAMES HEALTH AUTHORITY V SHEPPARD ROBSON AND OTHERS
650 _aSUBCONTRACTS