000 02037cab a2200229 4500
001 ABS67475
008 040303n2004 000 0 eng u
035 _a(Sirsi) u125310
100 _aBlackler, T.
245 _aHow late is too late?
260 _c2004
490 _aBuilding
_v269(8318) 6 February 2004, 60(1)
520 _aDiscusses the effects of the limitation acts on clients' claims, with reference to two cases. Describes how the standard forms of building contract contain many clauses requiring the parties to do things within time limits, and this concludes in the issuing of a final certificate. This contains time restrictions which if not challenged in a short period will have deemed to be certified. In "Cantrell and another v Wright and Fuller" ([2003] EWHC 1545 (TCC), [2003] BLR 412) a client was unhappy with a final certificate and claimed that the certificate was invalid because it was issued beyond the contract timetable and certain preliminary steps had not been taken. The judge decided that the time limits imposed by the contract were neither rigid or imputable so the architect had implied power to issue a certificate out of time. In "Merton LBC v Lowe" (CA, 18 BLR 130) the client had asked the architect to delay issuing the final certificate and when it was issued out of time the client argued it was invalid. The CA rejected this arguing that the client could not invalidate the final certificate by its own conduct. Advises that once a certificate is out of time there is an obligation to give notice to both parties before it can be issued. Clients and contractors can make representations about the contents of the certificate but other requirements of the contract are more rigid and immutable.
590 _aABS
650 _aCONTRACT DISPUTES
650 _aSTANDARD FORM OF BUILDING CONTRACT
650 _aCANTRELL AND ANOTHER V WRIGHT AND FULLER LTD
650 _aMERTON LBC V LOWE
650 _aTIME LIMITS
690 _aBUILT ENVIRONMENT-BUILDING CONTRACT FORMS
942 _n0
999 _c74223
_d74223