245 _aHold up!
260 _c2004
490 _aBuilding
_v269(8331) 7 May 2004, 50-51(2)
520 _aConsiders the issues raised by "Buxton Building Contractors Ltd v Durand Primary School" ([2004] EWHC 733 (TCC), [2004] ALL ER (D) 87 (Apr)). Argues that it gives a useful example of the reverse ambush effect in adjudication and considers whether the defendant's claim for damages, attached to its response to a formal adjudication notice requiring payment on an interim payment on an interim certificate, was an unfair ambush. The judge was concerned that the adjudicator had failed to consider all the evidence submitted about the cross claim and rules that the adjudicator only has jurisdiction to consider the evidence in the dispute which has been referred directly to him.
590 _aABS
650 _aBUXTON BUILDING CONTRACTORS V DURAND PRIMARY SCHOOL GOVERNORS
650 _aREVERSE AMBUSH
650 _aINTERIM CERTIFICATES
650 _aMANAGEMENT-DISPUTE AVOIDANCE, MANAGEMENT AND RESOLUTION-DISPUTE MANAGEMENT AND RESOLUTION-ALTERNATIVE DISPUTE RESOLUTION-ADJUDICATION
690 _aDispute resolution
_96236
942 _n0
999 _c74418
_d74418