| 245 | _aNEC ECC third edition - the expected key changes | ||
| 260 | _c2005 | ||
| 490 |
_aCivil Engineering Surveyor _vJune 2005, 45-46(2) |
||
| 520 | _aSummarises the key changes to the third edition of the New Engineering Contract: Engineering and Construction (NECECC) and raises questions over a number of issues, including including the submission of method contracts for all operations, the extension to the defects' correction period, compensation, choice of adjudication procedures and schedule of cost components. | ||
| 590 | _aIKA190705 | ||
| 690 | _aBUILT ENVIRONMENT-BUILDING CONTRACT FORMS-STANDARD FORMS OF BUILDING CONTRACT | ||