| 245 | _aMy slip, your fall | ||
| 260 | _c2005 | ||
| 490 | 0 |
_aBuilding _v270(8396) 2 September 2005, 56(1) |
|
| 520 | _aWarns about the changes in the NEC third edition regarding the circumstances relating to compensation that allow the contractor to claim additional time and money. Clause 61.3 bars a claim by the contractor if no notice is given within eight weeks of it becoming aware of the event in question. | ||
| 590 | _aIKA130905 | ||
| 650 | 2 | 4 | _aNEW ENGINEERING CONTRACT |