| 245 | 0 | 2 | _aA snowball's life |
| 260 | _c2006 | ||
| 490 | 0 |
_aArchitects' Journal _v223(4) 2 February 2006, 42(1) |
|
| 520 | _aLooks at the Technology and Construction Court's approach to contested applications to enforce adjudicator's decisions since the passing of the Housing Grants, Construction and Regeneration Act 1996. The reported cases show that the court is becoming increasingly reluctant to interfere with an adjudicator's decision, even where breach of natural justice is claimed. | ||
| 590 | _aIKA280206 | ||
| 600 | 2 | 4 |
_aa _FASTRACK CONTRACTORS LTD V MORRISON CONSTRUCTION LTD |
| 600 | 2 | 4 | _aLONDON AND AMSTERDAM PROPERTIES LTD V WATERMAN PARTNERSHIP LTD |
| 600 | 2 | 4 | _aAMEC CIVIL ENGINEERING LTD V SoS TRANSPORT |
| 650 | 2 | 4 | _aHOUSING GRANTS, CONSTRUCTION AND REGENERATION ACT 1996 |
| 650 | 2 | 4 | _aMACOB CIVIL ENGINEERING LTD V MORRISON CONSTRUCTION LTD |
| 650 | 2 | 4 | _aAUSTIN HALL BUILDING LTD V BUCKLAND SECURITIES LTD |
| 650 | 2 | 4 | _aCARILLION CONSTRUCTION LTD V DEVONPORT ROYAL DOCKYARD LTD |
| 650 | 2 | 4 | _aALL IN ONE BUILDING & REFURBISHMENTS LTD V MAKERS UK LTD |
| 690 | _aMANAGEMENT-DISPUTE AVOIDANCE, MANAGEMENT AND RESOLUTION-DISPUTE MANAGEMENT AND RESOLUTION-ALTERNATIVE DISPUTE RESOLUTION-ADJUDICATION-ADJUDICATION AWARDS | ||