| 000 | 01529cab a2200217 4500 | ||
|---|---|---|---|
| 001 | ABS38690 | ||
| 008 | 090401t1987 xxu||||| |||| 00| 0 eng d | ||
| 035 | _a(Sirsi) u11980 | ||
| 041 | _aeng | ||
| 245 | _aTemloc Ltd v Errill Properties Ltd | ||
| 260 | _c1987 | ||
| 350 | _a0 | ||
| 490 |
_aConstruction Industry Law Letter _v1987 CILL 376-377(2) |
||
| 520 | _aCA 29 July 1987. An appeal on a preliminary issue from a decision in the ORC. The contractors (T) agreed to erect retail units for the developers (E) under a JCT 1980 contract. In the appendix to the contract, there was an item "liquidated and ascertained damages", to be awarded under cl. 24.2 "at the rate" for which the figure had been filled in as " nil". T completed the work late. At issue was the construction of JCT 1980 cl 24 . T contended that liquidated damages were simply to be nil; E said that " nil" indicated that cl. 24 was to be excluded altogether from the contract. It was held in the CA, finding against E, that cl. 24 dealt comprehensively with the employer`s right to damages for late completion , whether liquidated or not. It was impossible to attribute to parties an intention that the employer should have the option of claiming unliquidated damages , when they had agreed that liquidated damages of the same character should be nil. | ||
| 650 | _aASCERTAINED DAMAGES | ||
| 650 | _aBUILT ENVIRONMENT-BUILDING CONTRACT FORMS | ||
| 650 | _aCLAIMS | ||
| 690 | _aBUILDING AND CONSTRUCTION-CASE LAW | ||
| 942 | _n0 | ||
| 948 | _c04/03/1997 | ||
| 999 |
_c7657 _d7657 |
||