000 02047cab a2200181 4500
001 ##L132871
008 060315n2006 000 0 eng u
035 _a(Sirsi) u132871
041 0 _aeng
245 0 0 _aScheldebouw BV v St James Homes (Grosvenor Dock) Ltd
260 _c2006
520 _a[2006] EWHC 89, TCC, 16 January 2006. SJ engaged S to install cladding on three buildings. The contract provided for a design team and construction manager; M were appointed construction manager, in a section which defined other entities and concluded with a power for SJ to appoint any further or other person. At a later date, SJ purported to appoint itself construction manager, and after disagreement between the parties, applied to the court for a declaration that it was entitled to do so under the contract. "Held" a decision-maker under a construction contract, who was not independent of the employer, was obliged to use his professional skills and best endeavours to reach the correct decision, rather than a decision favouring the employer's interests. Whilst an employer itself was not incapable of acting in such a manner, it was more difficult for it to make a decision contrary to its own interests. In this case, the whole structure of the contract had proceeded on the basis that employer and construction manager were different entities, and a large number of complexities were created if they were the same. Additionally, If SJ's interpretation were correct, then it would be entitled to dismiss all the design team, and act in their place, which would completely transform the agreement between the parties. In the circumstances, SJ was not entitled to appoint itself construction manager.
590 _aIKA280306
650 2 4 _aSCHELDEBOUW BV V ST JAMES HOMES (GROSVENOR DOCK) LTD
690 _aBUILT ENVIRONMENT-CONSTRUCTION MANAGEMENT-BUILDING CONTRACT ADMINISTRATION
856 4 1 _uhttps://www.bailii.org/cgi-bin/markup.cgi?doc=/ew/cases/EWHC/TCC/2006/89.html
_zView the item free of charge at www.bailii.org...
942 _n0
999 _c76668
_d76668