100 1 _aRowson, Stuart
245 0 0 _aIn the wake of Midland Expressway
260 _c2006
490 0 _aBuilding
_v271(8427) 21 April 2006, 70-71(2)
520 _aConsiders the implications of the decision in "Midland Expressway v Carillion Construction Ltd" ([2005] EWHC 2963, L132321) for PFI subcontracting. Examines the circumstances in which Equivalent Project Relief (EPR) provisions can be challenged, and the steps that can be taken by project companies to mitigate the risk of claims from subcontractors. These include share transfer restrictions, subordination of claims provisions, or inclusion of a longstop final date for any monetary EPR claims.
590 _aIKA250406
650 2 4 _aMIDLAND EXPRESSWAY V CARILLION CONSTRUCTION LTD AND OTHERS
690 _aMANAGEMENT-DISPUTE AVOIDANCE, MANAGEMENT AND RESOLUTION-DISPUTE MANAGEMENT AND RESOLUTION