| 000 | 01469cab a2200193 4500 | ||
|---|---|---|---|
| 001 | ABS38710 | ||
| 008 | 090401t1988 xxu||||| |||| 00| 0 eng d | ||
| 035 | _a(Sirsi) u12086 | ||
| 041 | _aeng | ||
| 245 | _aPanavia Air Cargo Ltd v Southend-on-Sea BC | ||
| 260 | _c1988 | ||
| 350 | _a0 | ||
| 490 |
_aEstates Gazette _v(8801) 9 January 1988, 60-64(3) |
||
| 520 | _aChD 30 July 1987. An originating summons by which tenants (P) sought a determination of the construction of the rent review provisions in a lease. At issue was the meaning of the construction of a provision which stated that if a rent review was not completed within 12 months of the commencement of a relevant period, the rent payable during that period would be the current rent increased by 25%. It was argued by P that as the review had not been completed in time, the automatic increase of 25% in the current rent came into effect. The landlords contended that this 25% provision was only an interim arrangement, and therefore, if a rent review was to be subsequently completed, the revised rent would take effect if it resulted in a figure over 125% of the rent payable for the previous period. On appeal, it was held that the increase of 25% did not operate automatically if the review was not completed within 12 months of the completion of the relevant period. | ||
| 650 | _aCONSTRUCTION OF CLAUSE | ||
| 690 | _aLANDLORD AND TENANT-CASE LAW-RENT REVIEWS | ||
| 942 | _n0 | ||
| 948 | _c04/03/1997 | ||
| 999 |
_c7734 _d7734 |
||