245 0 0 _aRepudiation, termination and quantum meruit
260 _c2006
490 0 _aConstruction Law Journal
_v22(4) 2006, 217-240(24)
520 _aDiscusses whether a contractor is entitled to recover money on a quantum meruit, rather than claim damages, for work done up to point of termination of a contract, and if so, whether the contract price, or the rates and prices specified in the contract, represent a constraint on the contractor's entitlement. Considers at length how the concept of quantum meruit has developed since the 19th century, and looks at its availability as a remedy.