245 0 0 _aAveat Heating Ltd v Jerram Falkus Construction Ltd
_h[electronic resource]
260 _c2007
520 _a[2007] EWHC 131 (TCC), 1 February 2007. Considered the validity of the adjudication clauses contained within the GC/Works contracts. Claimant (A) was engaged by defendant (J) to carry out works pursuant to a contract that incorporated GC/Works sub-contract conditions. The contract contained a clause that stated the adjudicator's decision would be valid even if issued after the time allowed. A dispute arose, A referred it for adjudication and the adjudicator awarded A the value of its claim plus its costs and expenses. J submitted that the contract clause was not compliant with the Housing Grants, Construction and Regeneration Act 1996 s108(2)(c). A applied to enforce the adjudicator's decision under the 1996 Act. "Held": the adjudicator's main decision was enforced as the adjudication provisions of the Scheme for Construction Contracts (SCC) applied instead of the contract clause. However, the adjudicator's decision regarding the parties' costs was not enforced as under the SCC an adjudicator has no jurisdiction to award a party its costs or expenses.
590 _aKA
650 2 4 _aAVEAT HEATING LTD V JERRAM FALKUS CONSTRUCTION LTD
650 2 4 _aEPPING ELECTRICAL CO LTD V BRIGGS AND FORRESTER (PLUMBING SERVICES) LTD
650 2 4 _aGC/WORKS SUBCONTRACT
650 2 4 _aHOUSING GRANTS, CONSTRUCTION AND REGENERATION ACT 1996 S108
650 2 4 _aSCHEME FOR CONSTRUCTION CONTRACTS
651 4 _aEngland and Wales
_y1543-
690 _aMANAGEMENT-DISPUTE AVOIDANCE, MANAGEMENT AND RESOLUTION-DISPUTE MANAGEMENT AND RESOLUTION-ALTERNATIVE DISPUTE RESOLUTION-ADJUDICATION
856 4 8 _uhttps://www.bailii.org/ew/cases/EWHC/TCC/2007/131.html
_zView the judgment free of charge at www.bailii.org...