| 245 | 2 | _aA way round insolvency | |
| 260 | _c1988 | ||
| 350 | _a0 | ||
| 490 |
_aContract Journal _v341(5651) 4 February 1988, 8(1) |
||
| 520 | _aConsiders direct payment clauses under which the employer has the option of paying nominated subcontractors if the main contractor fails to pay them. Case law is quoted throughout, paying particular attention to the decision in Re Jartay Developments Ltd , ChD 23 July 1982, see Abstract 31741. | ||
| 650 |
_aInsolvency _96247 |
||
| 650 | _aJCT 1980 CL 27 | ||
| 650 | _aJCT 1980 CL 35 | ||
| 650 | _aLIQUIDATION | ||
| 650 | _aRETENTION MONIES | ||
| 690 | _aBUILT ENVIRONMENT-BUILDING CONTRACT FORMS | ||