| 000 | 01942cad a22002055a 4500 | ||
|---|---|---|---|
| 001 | L138433 | ||
| 008 | 070606e20070320xxk f w 000 0 eng d | ||
| 035 | _a(Sirsi) u138433 | ||
| 041 | 0 | _aeng | |
| 245 | 0 | 0 |
_aClaymore Services Ltd v Nautilus Properties Ltd _h[electronic resource] |
| 260 | _c2007 | ||
| 520 | _a[2007] EWHC 805 (TCC), 20 March 2007. Considers the application of interest in the event of non-payment. Claimant contractor (C) issued proceedings against defendant property owner (N) for payment for building work carried out at N?s property. Prior to the trial, C had accepted there was no contract and claimed the sums should be paid as a quantum meruit, and it was agreed N would pay £750 000 to C. The court had to determine the period during which interest should apply and to fix an appropriate rate. C argued that interest should start to run from the date of completion of its works or from June 2004 when N had had time to consider C's final accounts. N contended that no interest should be payable until the sum due to C became apparent in December 2006. "Held": judgment in part for C. Where a claim was based in quantum meruit, interest for non-payment should only run from the date when the sum due was ascertainable, which in this case was June 2004. However, as C was guilty of unreasonable delay in commencing litigation, the interest payable to C should be reduced by 50% for one year. | ||
| 590 | _aKA | ||
| 650 | 2 | 4 | _aCLAYMORE SERVICES LTD V NAUTILUS PROPERTIES LTD |
| 651 | 4 |
_aEngland and Wales _y1543- |
|
| 690 | _aMANAGEMENT-DISPUTE AVOIDANCE, MANAGEMENT AND RESOLUTION-DISPUTE MANAGEMENT AND RESOLUTION-ALTERNATIVE DISPUTE RESOLUTION-ADJUDICATION | ||
| 690 | _aBUILT ENVIRONMENT-CONSTRUCTION MANAGEMENT-BUILDING CONTRACT ADMINISTRATION | ||
| 856 | 4 | 0 |
_uhttps://www.bailii.org/cgi-bin/markup.cgi?doc=/ew/cases/EWHC/TCC/2007/805.html _zView the judgment free of charge at www.bailii.org... |
| 942 | _n0 | ||
| 999 |
_c78869 _d78869 |
||