| 520 | _aExplains how rights of recovery have acquired collateral warranties. However, legislation has removed the need for these by allowing parties to contract out of the privity of contract rule, thus saving cost and time. Concludes that the construction industry is becoming increasingly keen to use the Contracts (Rights of Third Party Act) 1999. (See also L139926). | ||