245 0 0 _aRingway Infrastructure Services Ltd v Vauxhall Motors Ltd No 2
_h[electronic resource]
260 _c2007
520 _a[2007] EWHC 2507 (TCC), 30 October 2007. The claimant contractor (R) was employed by the defendant (V) to carry out various works in connection with a vehicle distribution centre. R had referred a dispute to adjudication after V had not responded to its final application for interim payment, and the adjudicator had ordered V to pay R £1 303 704.95 plus VAT and interest together with his fees and expenses. V claimed the adjudicator lacked jurisdiction, but the court determined the adjudicator had had jurisdiction and that R was contractually entitled to the net sum claimed in the absence of a notice from V ([2007] EWHC 2421 (TCC)). R then submitted that the adjudicator had awarded interest from a later date and that the court had a discretion under the Supreme Court Act 1981 s35A to make an additional award of interest from the earlier date. V submitted that R's claim was for the enforcement of the adjudicator's decision and this should be complied with. "Held": the cause of action to enforce an adjudicator's award was contractual and the date when that cause of action arose was the date when V failed to honour the adjudicator's decision. Judgment accordingly.
590 _aKA
650 2 4 _aRINGWAY INFRASTRUCTURE SERVICES LTD V VAUXHALL MOTORS LTD NO 2
650 2 4 _aSUPREME COURT ACT 1981 S35A(1)
650 2 4 _aJCT STANDARD FORM OF BUILDING CONTRACT WITH CONTRACTORS DESIGN (1998 EDITION)
651 4 _aEngland and Wales
_y1543-
690 _aMANAGEMENT-DISPUTE AVOIDANCE, MANAGEMENT AND RESOLUTION-DISPUTE MANAGEMENT AND RESOLUTION-ALTERNATIVE DISPUTE RESOLUTION-ADJUDICATION
856 4 0 _uhttps://www.bailii.org/ew/cases/EWHC/TCC/2007/2507.html