_aLead times _bNov 2007-Feb 2008 |
| 260 | _c2008 | ||
| 490 | 0 |
_aBuilding _v273(8516) 15 February 2008, 68-69(2) |
|
| 520 | _aGives details of lead times for various products, including piling, concrete works, structural steel frames, cladding and roofing. The period between November 2007 and February 2008 saw a return to more normal lead times, with eight packages reducing their lead times and only four reporting a rise. This is partly due to the number of major projects being deferred or delayed. | ||