| 245 | 0 | 0 |
_aCost model _blaboratories |
| 260 | _c2008 | ||
| 490 | 0 |
_aBuilding _v273(8517) 22 February 2008, 68-75(8) |
|
| 520 | _aLooks at the key issues and costing involved in the construction of laboratories. Outlines key design issues, the practical planning of laboratory facilities, servicing strategies for laboratories, sustainability, and cost drivers. The cost model breakdown is based on a university-funded research laboratory, with a gross floor area of 12 600m2. | ||
| 590 | _aKA | ||
| 651 | 4 |
_aUnited Kingdom _y |
|
| 690 | _aBUILT ENVIRONMENT-BUILDING COSTS | ||
| 710 | 2 |
_aDavis Langdon _94649 |
|