245 0 4 _aThe enforcement of adjudicators' awards under the Housing Grants Construction and Regeneration Act 1996 part 27
260 _c2008
490 0 _aArbitration
_v74(2) May 2008, 181-187(7)
520 _aComments on a range of issues arising from decisions in cases where the enforcement of adjudicator's awards are reviewed. Issues covered include: oral variation of construction contracts; terms in writing of construction contracts; effect of decision; interest on payments; when payments due; withholding payment. Uses several specific cases as examples and comments on them in light of the issues they raised. (See also: L141909; L142227; L139846; L141911; L143203).
590 _aKA
650 2 4 _aTREASURE AND SON LTD V MARTIN DAWES
650 2 4 _aHARRIS CALNAN CONSTRUCTION CO. LTD V RIDGEWOOD (KENSINGTON) LTD
650 2 4 _aLEDWOOD MECHANICAL ENGINEERING LTD V (1) WHESSOE OIL AND GAS AND (2) VOLKER STEVIN CONSTRUCTION EUROPE BV
650 2 4 _aBOTHMA V MAYHAVEN HEALTHCARE LTD
650 2 4 _aRINGWAY INFRASTRUCTURE SERVICES LTD V VAUXHALL MOTORS LTD NO 2
650 2 4 _aPC HARRINGTON CONTRACTORS LTD V MULTIPLEX CONSTRUCTIONS (UK) LTD
650 2 4 _aHOUSING GRANTS, CONSTRUCTION AND REGENERATION ACT 1996