| 245 | _aResolving disputes under UK construction contracts | ||
| 260 | _c1996 | ||
| 350 | _a0 | ||
| 490 |
_aArbitration and Dispute Resolution Law Journal _v(1) March 1996, 3-24(21) |
||
| 520 | _aExamines proposals for change in civil engineering contract dispute resolution procedures, including a comparision of the traditional ICE conditions of contract and the NEC/EEC. | ||
| 650 | _aCONSTRUCTION DISPUTES | ||
| 650 |
_aContracts _96232 |
||
| 650 |
_aDISPUTE RESOLUTION _96236 |
||
| 650 | _aENGINEERING AND CONSTRUCTION CONTRACT | ||
| 650 | _aICE CONDITIONS OF CONTRACT | ||
| 650 | _aNEW ENGINEERING CONTRACT | ||
| 690 | _aBUILT ENVIRONMENT-BUILDING CONTRACT FORMS | ||