_aCost management _bthe new rules |
| 260 | _c2009 | ||
| 490 | 0 |
_aBuilding _v273 (8572) 27 March 2009, 63 (1) |
|
| 520 | _aPresents the RICS New Rules of Measurement: order of cost estimating and elemental cost planning, a new instrument for calculating costs of a construction project. In addition to guidance for costs estimating and cost planning, they include advice on how to deal with preliminaries, overheads and profit, risk allowances and inflation. Explains the benefits of these new rules. They will be effective from 1 May 2009. | ||