100 1 _aMoone, Brian
245 0 0 _aLead times
_bJanuary-March 2009
260 _c2009
490 0 _aBuilding
_v274(8573) 3 April 2009, 60-61 (2)
520 _aReports that lead times remain the same for all categories, except concrete works and specialist joinery. Lead times for concrete works decreased to nine weeks. They were reduced to 14 weeks for specialist joinery. Gives details of lead times for various products including piling, concrete works, structural steel frames, cladding and roofing.