245 0 4 _aPT Building Services Limited v ROK Build Limited
_h[electronic resource]
260 _c2009
520 _a[2008] EWHC 3434 (TCC), 08 December 2008. The case considers whether a party is irrevocably bound by his choice. ROK Build Limited (R) engaged PT Building Services Limited (P) to carry out works for it. They had a dispute over their contract brought to adjudication. P sought enforcement of an adjudicator's decision. R resisted enforcement of this decision on the grounds that the adjudicator had no jurisdiction. P issued a notice of second adjudication. R objected that the second adjudicator had no jurisdiction because the grounds of dispute had already been dealt with by the first adjudication. The second adjudicator resigned. P argued that this argument meant that R was accepting the decision of the first adjudicator as valid and binding. "Held": The judge decided that by using the first decision to persuade the second adjudicator to resign, R was accepting his decision as valid and binding. R could not now resist this first decision in enforcement proceedings.
590 _aKA
650 2 4 _aPT BUILDING SERVICES LIMITED V ROK BUILD LIMITED
650 2 4 _aNIKKO HOTELS (UK) LTD V MEPC PLC
650 2 4 _aBOUYGUES UK LTD V DAHL-JENSEN UK LTD
650 2 4 _aCARILLION CONSTRUCTION LTD V DEVONPORT ROYAL DOCKYARD LTD
650 2 4 _aHART INVESTMENTS LTD V FIDLER AND ANOTHER
650 2 4 _aCOLLINS (CONTRACTORS) LTD V BALTIC QUAY MANAGEMENT (1994) LTD
650 2 4 _aAMEC CIVIL ENGINEERING LTD V SOS TRANSPORT
651 4 _aEngland and Wales
_y1543-
690 _aMANAGEMENT-DISPUTE AVOIDANCE, MANAGEMENT AND RESOLUTION-DISPUTE MANAGEMENT AND RESOLUTION-ALTERNATIVE DISPUTE RESOLUTION-ADJUDICATION
856 4 0 _uhttps://www.bailii.org/ew/cases/EWHC/TCC/2008/3434.html