245 0 0 _aBarratt Homes Ltd. v DWR Cymru Cyfyngedig (Welsh Water)
_h[electronic resource]
260 _c2008
520 _a[2008] EWCA Civ 1552. This case reinforces the established position that land-owning developers have a statutory right to connect into a public sewer. The water undertaker (D) was not permitted under the Water Industry Act 1991 s.106 to require a developer (B) to connect to its sewers at an alternative point than that proposed by the developer, in order to avoid sewer overload. B wanted to connect the drains at point x adjoining its development site. D objected as this might overload the sewers at point x, and suggested that the sewers be joined at point y, 300-400 metres further down the sewer, not adjoining the development.
590 _aKA NTK
650 2 4 _aBARRATT HOMES
650 2 4 _aWATER INDUSTRY ACT 1991 S106
651 4 _aEngland and Wales
_y1543-
690 _aENVIRONMENTAL AND LAND CONSULTANCY-WASTE MANAGEMENT
856 4 0 _uhttps://www.bailii.org/ew/cases/EWCA/Civ/2008/1552.html
_zView the case free of charge at www.bailii.org