| 245 | 0 | 0 | _aCost control in the Chinese construction sector |
| 260 | _c2010 | ||
| 490 |
_aProject Control Professional _v48(5) September 2010, 16-22(7) |
||
| 520 | _aHistory of cost control and cost engineering in China; the cost control process normally involves 5 key stages, feasibility stage, preliminary design stage, detailed design stage, construction stage, and post-completion stage; the tendering and bidding system; bills of quantities and all-in rates; contract forms; qualification control. | ||