245 0 0 _aAre liquidated damages payable post termination?
260 _c2010
490 _aCivil Engineering Surveyor
_vOctober 2010, 38-39(2)
520 _aLooks at how the judgment in Hall v van der Heiden (2010) has cast doubt on liability for liquidated damages or general damages for any delay continuing beyond termination; compensating an employer for late completion.