| 245 | 0 | 0 | _aThere are ways around "pay now, argue later" |
| 260 | _c2011 | ||
| 490 |
_aConstruction News _v(7214) 21 April 2011, 35(1) |
||
| 520 | _aIf an adjudicator decides that you owe money to another party, regardless of whether you consider it right or wrong the decision is temporarily binding and must be complied with until either party commences court or arbitration proceedings to reassess and finally determine the dispute; The Construction Act; Straw Realisations v Shaftesbury House (Developments). | ||
| 590 | _aKA | ||
| 651 | 4 |
_aUnited Kingdom _y |
|
| 690 | _aMANAGEMENT-DISPUTE AVOIDANCE, MANAGEMENT AND RESOLUTION-DISPUTE MANAGEMENT AND RESOLUTION-ALTERNATIVE DISPUTE RESOLUTION-ADJUDICATION | ||