520 _aExplains the development and use of dispute boards; DRB or dispute recommendation boards which originate in the USA; DAB or dispute adjudication boards which are being used increasingly with the globalisation of adjudication during projects; the FIDIC DAB; benefits of a dispute board; cost; recommended elements for a successful dispute board; dispute avoidance.