245 0 0 _aJerram Falkus Construction Ltd v Fenice Investments Inc
_h[electronic resource]
260 _c2011
520 _a[2011] EWHC 1935 (TCC), 21 July 2011. For the reasons given in Section 5, it is not open to JFC to challenge the decision in the third adjudication. They are therefore not entitled to make any further delay-related claim. It would also mean that Fenice is entitled to liquidated damages as set out. The other two conclusively arguments, one raised by each side, must fail.