| 100 | _aPowell-Smith, V. | ||
| 245 | _aRisks of own conditions | ||
| 260 | _c1988 | ||
| 350 | _a0 | ||
| 490 |
_aContract Journal _v14 April 1988, 7(1) |
||
| 520 | _aAnalyses the recent case of Chichester Joinery Ltd v John Mowlem & Co Plc where the parties attempted to contract by exchanging orders and acknowledgements each of which purports to be on the usual terms of the party putting it forward - a concept known as battle of forms. | ||
| 650 | _aBUILT ENVIRONMENT-BUILDING CONTRACT FORMS | ||
| 650 | _aCLAIMS | ||
| 650 | _aTERMS OF CONTRACT | ||
| 690 | _aBUILT ENVIRONMENT-BUILDING CONTRACT FORMS | ||