245 2 _aA critical examination of the designer`s role under the ICE Design and Construct Conditions of Contract and the Highways Agencies Design and Build Conditions of Contract
260 _aLondon
_bRICS
_c1999
300 _aii, 24p.
_c30cm.
350 _a7.95
490 _aRICS Foundation Research Papers
_v3(2)
520 _aResearch indicating that Highways Agency designers have far more responsibility than their ICE counterparts because of the supervisory and certifying role that is demanded by the Agency, whereas the ICE designers need not be site based at all.
650 _aDESIGN AND BUILD CONTRACTS
650 _aDESIGNERS
650 _aENGINEERING CONTRACTS
650 _aHIGHWAYS AGENCY
650 _aICE DESIGN AND CONSTRUCT CONDITIONS OF CONTRACT
690 _aBUILT ENVIRONMENT-BUILDING CONTRACT FORMS
700 _aHodgson, Geoffrey
700 _aJeffrey, J. A.