Harbour & General Works Ltd v Environment Agency
Series: Construction Industry Law Letter ; [1999] CILL 1556-1559Publication details: 1999Subject(s): Summary: CA 12 October 1999. Extension of time in which to commence arbitration under Arbitration Act 1996 s12. 'Final & binding' under ICE conditions of contract, clause 66. ICE Arbitration procedure, rule 5.2. (Taken from journal headnote)| Item type | Current library | Call number | Copy number | Status | Barcode | |
|---|---|---|---|---|---|---|
| Law report | London Journal article | X103346 (Browse shelf(Opens below)) | 1 | Available | 103346-1001 |
CA 12 October 1999. Extension of time in which to commence arbitration under Arbitration Act 1996 s12. 'Final & binding' under ICE conditions of contract, clause 66. ICE Arbitration procedure, rule 5.2. (Taken from journal headnote)