Contract? what contract?
Language: English Series: Contract Journal ; 433(6574) 10 May 2006, 18(1)Publication details: 2006Subject(s): Summary: Discusses "ERDC Group Ltd v Brunel University" ([2006] EWHC 687 TCC, L133495), where it was held that, in circumstances where no contract for works existed after a specific date, the contractor was entitled to be paid on a quantum meruit basis, but calculated by reference to tendered rates and prices prevailing before the contract expired.| Item type | Current library | Call number | Copy number | Status | Barcode | |
|---|---|---|---|---|---|---|
| Journal article | London Journal article | L133500 (Browse shelf(Opens below)) | 1 | Available | 133500-1001 |
Discusses "ERDC Group Ltd v Brunel University" ([2006] EWHC 687 TCC, L133495), where it was held that, in circumstances where no contract for works existed after a specific date, the contractor was entitled to be paid on a quantum meruit basis, but calculated by reference to tendered rates and prices prevailing before the contract expired.